ANGGARAN BIAYA YANG DIBUTUHKAN PEMBANGUNAN AULA MASYARAKAT

ANGGARAN BIAYA YANG DIBUTUHKAN
DALAM PEMBANGUNAN AULA MASYARAKAT KELURAHAN HUTARAJA
KECAMATAN MUARA BATANGTORU 
NO BAHAN VOLUME SATUAN HARGA SATUAN JUMLAH
I Pembangunan Aula         
1 Batu Kali 25 M3                200,000               5,000,000
2 Batu Bata 32400 Biji                        700            22,680,000
3 Pasir 75 M3                120,000               9,000,000
4 Sirtu 10 M3                200,000               2,000,000
5 Semen 250 Zak                  70,000            17,500,000
6 Semen Putih 10 Zak                120,000               1,200,000
7 Besi Uk. 12 Inci 93 Batang                  90,000               8,370,000
9 Besi Cincin 93 Batang                  20,000               1,860,000
10 Kawat Pengikat 10 Kg                  30,000                  300,000
11 Keramik 180 Kotak                  70,000            12,600,000
12 Kayu Ukuran 5 x 7 x 4 m 60 Batang                  90,000               5,400,000
13 Kayu Ukuran 4 x 6 x 4 m 200 Batang                  40,000               8,000,000
14 Kayu Ukuran 4 x 12 x 4 m 60 Batang                100,000               6,000,000
15 Kayu Ukuran 4 x 4 x 4 m 150 Batang                  22,000               3,300,000
16 Papan Cor 1 M3            4,000,000               4,000,000
17 Lesplang 30 Batang                  80,000               2,400,000
18 Les Asbes 120 Batang                  10,000               1,200,000
19 Asbes 80 Lembar                  80,000               6,400,000
20 Seng Genteng (Multi Sirap) 180 Lembar                250,000            45,000,000
21 Rabung  20 Lembar                  70,000               1,400,000
22 Rangka Atap 1 Set          20,000,000            20,000,000
23 Paku  20 Kg                  30,000                  600,000
24 Kunci + Engsel 1 Set            2,000,000               2,000,000
25 Cat Tembok Uk. 25 Kg 6 Kaleng                360,000               2,160,000
26 Cat Minyak 14 Kaleng                  55,000                  770,000
27 Pipa Paralon 4 Batang                  70,000                  280,000
28 Kloset 2 Buah                150,000                  300,000
29 Kran 1 Set                300,000                  300,000
30 Mesin Air 1 Buah          15,000,000            15,000,000
31 Pintu 2 Buah            1,200,000               2,400,000
32 Jendela  4 Buah                450,000               1,800,000
33 Pintu Piber Kamar Mandi 2 Buah                300,000                  600,000
34 Upah Tukang                  50,000,000
35 Meteran + Instalasi 1 Set            8,000,000               8,000,000
36 Biaya Operasional                     9,000,000
Jumlah I                276,820,000
II Pembuatan Lokasi Parkir 3 x 6 m        
1 Seng 1 Kodi                950,000                  950,000
2 Semen 20 Zak                  70,000               1,400,000
3 Pasir 6 M3                120,000                  720,000
4 Batu Kali 5 M3                200,000               1,000,000
5 Upah Tukang                     1,500,000
Jumlah II                     5,570,000
III Perlengkapan Aula         
1 Meja  2 Buah                450,000                  900,000
2 Kursi Plastik 200 Biji                  60,000            12,000,000
3 Papan Tulis White Board 1 Buah                500,000                  500,000
Jumlah III                  13,400,000
Jumlah Keseluruhan (I + II + III)                295,790,000
Hutaraja,      April 2013
PANITIA PEMBANGUNAN AULA
KELURAHAN HUTARAJA
  KETUA     SEKRETARIS  BENDAHARA
 HENRIK HARAHAP HASRAN NASUTION      ISNAN PULUNGAN
DIKETAHUI OLEH:  DIKETAHUI OLEH,  DIKETAHUI OLEH,
CAMAT MUARA BATANGTORU LURAH HUTARAJA KEPLING
ARMAN PASARIBU, S.Sos A B U    A K H I R SUDIRMAN NASUTION
NIP. 19700805 199308 1 001  NIP. 19600906 198201 1 004
PENATA TK. I 